Visual History
On 10 April 1997, the Implementation Planning Group visited the
Harvard Depository for a first-hand view of
how a shelving facility works. Shown below are (left to right)
Diane Abbott, Paul Stuehrenberg, Sue Crockford-Peters, Anthony Riccio, Mary
LaFogg, Gail Harris, Carol Jones, Susan Burdick, Tom Schneiter, and Steven
Arakawa.
Click
here for a visual summary of the trip's
highlights.
Below is an aerial view of the location before
construction began.
As work begins, Project Superintendent Robert LeBel and
Project Manager Gregory O. Bliss discuss site details with architect Bruce
Scott.
An official "ground-breaking" ceremony was held on 31
March 1998 in the Sterling Memorial Library Lecture Hall. Following a
presentation on the building and the project to library staff by architect
Bruce Scott, several dignitaries symbolically turned over the dirt (brought
from the Hamden site). From right to left (with shovels) are Associate Provost
Lloyd Suttle, Sue Crockford-Peters (Head, Cross Campus Library), University
Librarian Scott Bennett, followed by Bruce Scott, John Vincenti, Manager
of Building Operations and Security for the Library, and Danuta Nitecki,
Associate University Librarian. Sue was selected in a random drawing to represent
library staff in this festive event.
On 31 March 1998, construction of the Library Shelving Facility began at
147 Leeder Hill Drive, Hamden, Connecticut. Barr & Barr, Inc. is the
General Contractor responsible for construction.
6-5-98: A mason is about to start the next layer of block around the
two loading dock entrances that are taking shape.
6-5-98: Outer walls to the processing area are being built.
6-5-98: Workers are building the wall of the processing area with openings
for future entrances to the shelving modules.
6-5-98: The walls of the shelving module are built about half-way to their
30 foot heights. As the wheelbarrow illustrates, this is becoming a really
large space.
6-16-98: Walls of the shelving module are now approximately 20 ft. high and
require bracing until the roof is installed.
7-2-98: Cables and braces support the walls of the shelving module while
the steel roof trusses are being positioned.
7-2-98: This view of the loading docks shows the height of the shelving module
behind the processing area and the crane used to place the module's roof
trusses in place.
7-21-98: Architect Bruce Scott is pleased to see that the processing area
and the shelving module have reached their full heights.
 |
A group of Yale University Library staff visited the Cornell University
Library Annex on 28 July 1998. |
| Click
here for a visual summary of the trip's
highlights. |
8-4-98: The processing area floor has been poured ...
8-4-98: ... and the floor surface is being smoothed.
8-4-98: The ground in the shelving module is prepared for the upcoming pour
of the super-flat slab floor.
8-11-98: The levelness of the floor was repeatedly measured with a transit
mounted on a tripod.
| 8-11-98: The superflat slab in the shelving module was poured
in several sections over three days. After the concrete was poured, men worked
to spread and then smooth it further with a steel beam.
|
 |
 |
8-18-98: Duct work is mounted close to the roof of the shelving module.
| 9-15-98: John Vincenti confirms that all's in place on the roof. |
 |
| 9-29-98: The exterior surface is almost complete as the driveway is being
prepared. |
|
9-29-98: Project managers Robert LeBel and Gregory O. Bliss from Barr &
Barr are pleased to show us that walls are up in the processing area.
 |
9-29-98: Architect Bruce Scott examines the deposited loam to be spread
for the front lawn. |
| 10-13-98: Appliances have arrived for the break room, where colored tiles
have been installed as well. |
 |
10-27-98:
From either perspective, the processing area looks big without furniture,
staff or materials. |
The processing area can be viewed from the break room. |
 |
 |
 |
10-27-98: Uprights for the shelving create interesting patterns. |
10-27-98: The telecommunication switchboards are being examined in the electric
room.
10-27-98: The first use of the (almost completed) Library Shelving Facility
conference room was hosting today's construction meeting. In attendance,
left to right: John Vincenti, Manager of Building Operations and Security
for the Library; Richard Vollaro, Senior Mechanical Engineer, Yale Office
of Facilities; Robert Lebel, Project Superintendent; Gregory O. Bliss, Project
Manager; Bruce Scott, architect; and Danuta Nitecki, Associate University
Librarian (not shown).
10-27-98: Landscapers are planting shrubs and trees to screen the Library
Shelving Facility from view of Putnam Street residents.
10-30-98: Furniture has arrived
|
|
for the staff break room |
|
|
|
|
|
and for the offices. |
 |
|
|
|
|
|
 |
10-30-98: Partitions are in place to define the processing areas.
| 11-17-98:
The Library Shelving Facility exterior is
completed and its parking spaces used.
Notice the Yale blue strip around the
shelving module. |
Completed loading docks are ready to receive materials. |
 |
 |
11-24-98: The Library Shelving Facility operations will be in good hands
under the leadership of Mike DiMassa, Manager (right) and Marvin Tillman,
Materials Assistant (left).
 |
11-24-98: John Vincenti (left) and Rob LeBel (right) are pleased to see
workbenches and other details in place. |
| 11-24-98: Consultant Reese Dill reviews with Mike DiMassa his recommendations
for arranging materials on the shelves according to his "plannograph." |
 |
11-24-98: Reese Dill illustrates how a shelf is installed.
11-25-98: The Library Shelving Facility staff spent their day today being
trained in operating the order picker. Pictured left to right are Marvin
Tillman, Tania Grant-Lopes, Gareth Gibson, John Giamattei, Jim Esposito and
Mike DiMassa.
| 11-25-98: Tania is learning to operate the Raymond order picker during
training. |
|
| 12-11-98: Chris Brennan from Generation Fifth Applications
spent the week training staff ... and showed her affection for the system
as she prepared to leave the Library Shelving Facility. |
 |
 |
Return to the
top of this visual tour.
Yale University
Library
Copyright
Last modified: 16 November 1999
Comments:
danuta.nitecki@yale.edu
This file is located at http://www.library.yale.edu/lsf/visual.html