Orbis2 Training Notes

January 9th, 2002

 

 

SCOPA presentation:

Order of presentation will be:  Kalee on Data Migration, Ellen on WebVoyage, Cindy on Acq, Patricia on Cat, Marybeth on Circ, Audrey wrap-up w/ updates on hardware, training, location mapping, workstation upgrades and Feb data conversion.

 

UPDATES:

Hardware: All the servers have arrived. Sun is building the racks today. For the Production servers the T3's and operating system will be installed next week.  Oracle and Voyager will be installed the week of Jan 21. Endeavor is coming for the Oracle/Voyager installation on Jan 22-23.  ITS will install the development server after production.  Test servers will be last.

 

Training contract with NELINET was approved by Alice.  Our survey suggests that we will need 60 days of training prior to going live.  Am estimating 18 days of training after July 16th.  We will use the SCML for most of the training, but I want to run simultaneous classes for 10 days in order to build a cushion into the training schedule.  Kate is looking for alternate training locations.

 

DRESS REHEARSAL CONVERSION

Audrey will schedule a conference call with Endeavor and the Chairs group to review the dress rehearsal conversion schedule.  Imp groups must have sysadmin values defined in order to enter them at key times during the conversion. 

 

These dates are:

2/26 - Cat sysadmin, security, WebVoyage

3/7  - Acq sysadmin

3/25 - Circ sysadmin

 

CINDY AND SHAWN TO CONTINUE TO INVESTIGATE PRINTING NEEDS