Orbis2 System Criteria
 
 
 
Project Start:
Project Finish:
Thu 6/1/00
Mon 8/21/00
 
Tasks  
ID Task Name Duration Start Finish Resource Names % Complete
1
Working Group chair identified
1 day Thu 6/1/00 Thu 6/1/00   0%
2
Working group members identified
2 days Fri 6/2/00 Mon 6/5/00   0%
3
Invitations for Members sent
1 day Tue 6/6/00 Tue 6/6/00   0%
4
Invitations for members Acknowledged
2 days Wed 6/7/00 Thu 6/8/00   0%
5
Kickoff Orbis2 Systems Criteria Workgroup
1 day Fri 6/9/00 Fri 6/9/00   0%
6
Review background material
1 day Mon 6/12/00 Mon 6/12/00   0%
7
Organizational drafts of subject material by subgroups
4 days Tue 6/13/00 Fri 6/16/00   0%
8
First ILS demo (III)
1 day Tue 6/13/00 Tue 6/13/00   0%
9
Second ILS demo (sirsi)
1 day Tue 6/20/00 Tue 6/20/00   0%
10
First Review meeting
1 day Wed 6/21/00 Wed 6/21/00   0%
11
Third ILD demo (endeavor)
1 day Thu 6/22/00 Thu 6/22/00   0%
12
First Drafts of subgroup material
3 days Fri 6/23/00 Tue 6/27/00   0%
13
Fourth ILS demo (ex libris)
1 day Thu 6/29/00 Thu 6/29/00   0%
14
Second Review meeting
1 day Fri 6/30/00 Fri 6/30/00   0%
15
First Working group Draft (to MMG)
0 days Fri 6/30/00 Fri 6/30/00   0%
16
ALA meetings with vendors
2 days Fri 7/7/00 Mon 7/10/00   0%
17
Feedback from ALA attendees
1 day Tue 7/11/00 Tue 7/11/00   0%
18
Second subgroup organizational drafts
5 days Wed 7/12/00 Tue 7/18/00   0%
19
Second Workgroup organizational meeting
5 days Wed 7/19/00 Tue 7/25/00   0%
20
Second subgroup draft
5 days Wed 7/26/00 Tue 8/1/00   0%
21
Second Work Group draft
5 days Wed 8/2/00 Tue 8/8/00   0%
22
Final Draft
5 days Wed 8/9/00 Tue 8/15/00   0%
23
Final Criteria to MMG
0 days Mon 8/21/00 Mon 8/21/00   0%
   
Resources  
ID Name Group Max Units Peak Units
   
Assignments  
Task ID Task Name Resource Name Work Start Finish % Work Complete