Preparing
for Commencement and Beyond, cont.

New
plantings have been returned along Berkeley
College.

The
roof of the garden pavilions in the Berkeley College
courtyards are being returned to their original heights,
before the Cross Campus Library was built.

The
walls of the new northeast pavilion entrance to Cross
Campus Library are beginning to rise.

The
stairs from the northeast pavilion to the cafe lounge
entance have been poured.

Foundations
and waterproofing are being installed
for the glass southeast entance to the Cafe Study
Lounge from the exterior.

Within
the library, the main stairwell is framed and will
provide an easy access to the lower level.

These
central stairs will come from two sides and then turn
for access to the lower level.
See next page
|