Logistics Plans for the Cross Campus Construction Zone

The blue lines on the following plans indicate the boundary of the construction site where barriers will be installed.

Please be cautious when walking in this area.

Download a pdf copy of the logistics plan for May 2006 to September 2006 (Revised 6/13/06).

During first four months of renovation truck movement to remove debris from the CCL and delivery materials to the site will take place off of Wall Street on both sides of Berkeley College.

Download a pdf copy of the logistics plan for October 2006 to Summer 2007 (Revised 6/13/06).

During the remainder of construction (October 2006 - Summer 2007), most of the truck traffic will move from Wall Street between Berkeley College and WLH.

   Return to the Phase 2a Renovations Homepage.
   
Return to Yale University Library Homepage.


 bottom quick links
© 2006 Yale University Library
This file last modified 06/13/06
Send comments about this site to
Library Administration
Phase 2a Renovations Copyright Project Overview Fact Sheet photos Donor News & Information Responses
Search this site Yale University YaleInfo Contact Us Orbis Library Catalog Library hours