Logistics Plans for the Cross Campus Construction Zone
The
blue lines on the following plans indicate the boundary
of the construction site where barriers will be installed.
Please be cautious when walking in this area.
Download a pdf copy of the logistics plan for May 2006 to September 2006 (Revised 6/13/06).
During
first four months of renovation truck movement to remove debris
from the CCL and delivery materials to the site will take
place off of Wall Street on both sides of Berkeley College.
Download a pdf copy of the logistics plan for October 2006 to Summer 2007 (Revised 6/13/06).
During
the remainder of construction (October 2006 - Summer 2007),
most of the truck traffic will move from Wall Street between
Berkeley College and WLH.
|